THE PARK - CENTRE FOR MENTAL HEALTH - HYDRAULIC UPGRADE

CLIENT: WEST MORETON HOSPITAL & HEALTH SERVICES
October 2016 - June 2017

Bellrise Principal Contractor of Design, Supply and Construct new fire main and water mains for “The Park – Centre for Mental Health”.

The works included:

  • Around 3600m of water mains

  • 2000m of fire mains

  • Between 50mm and 250mm including electrical pumps,

  • Two large water storage holding tanks

  • A pump station building complete with pumps and electrical scada.