07 5467 1011

©2019 by Bellrise Investments. Proudly created with Wix.com

Feature projects

All services provided by Bellrise Investments are done so with quality and care. Bellrise's projects cover multiple disciplines in the civil pipeline construction industry. Check out our selection of projects to give you a taste of what we can achieve.

Bellrise Principal Contractor of Design, Supply and Construct new fire main and water mains for “The Park – Centre for Mental Health”.

The works included:

  • Around 3600m of water mains

  • 2000m of fire mains

  • Between 50mm and 250mm including electrical pumps,

  • Two large water storage holding tanks

  • A pump station building complete with pumps and electrical scada.

Repair the damaged sections of gabion rock boxes/mattresses and completely replace the missing sections. The repaired section shall be connected to the existing Gabions and river banks.

Installation of 2 x new flow meter pits and the supply, removal and replacement with a new 600mm mag flow meter.

  • Construstion of a pre-cast concrete pit around the DN600 flow meter

  • Construction of a pre-cast concrete pit around the DN750 flow meter

  • Renewal of the 600mm mag flow meter

Pipework associated with the construction of a new development site at Rothwell

  • Supply and installation of 573m of DN160 PE gravity fed sewer pipe

  • Verify location of all existing services

  • All sewer lines to be tested on completion

  • Liaise with Unity Water regarding live connections

  • Construction of 9 x Manholes

  • All dewatering and groundwater control and disposal of surface water

  • Compaction testing

The Big Fish Development consisted of;
Site Establishment
Traffic Control
Survey
Dewatering of Trenches
Restoration of surfaces
Testing
Supply, lay and joint Trunk Water Main 1875m of PE100 PN16 DN315, 70m of PE100 PN16 DN160 & 20m of PE100 PN20 DN315
Supply, lay and joint Sewer Pressure Mains including - 320m of PE100 PN16 DN63, 2020m of PE100 PN16 DN75 & 60m of PE100 PN20 DN75
1 x DN100mm hydrant tee with riser and spring hydrant
6 x DN150mm sluice valves
2 x DN315mm sluice valves
2 x DN315mm scour valves
2 x DN315mm air valves
2 x boundary connection kits
7 x flushing points
3 x gas release chambers
7 x sluice valves
Trenchless excavation under Kink John Creek

Construction of; 1700m of 300mm DICL pipe and installation of pump stations at each end of the works with a deep lne running over the edge of a 70m deep quarry finishing on the floor.
Blasting and 18m long rock nails were used to stabilise the rock face are where the pipe was attached. Pumps and electrical were also supplied with this contract.